PM Risk

Risk register management for civil engineering projects. Full lifecycle: identify → score → assign → mitigate → monitor → escalate → close.


Risk Register Format

Each risk record:

RISK RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID:               R-[NNN]
Category:         [TECHNICAL / COMMERCIAL / PROGRAMME / HSE / REGULATORY / EXTERNAL]
Description:      [what could happen and what the consequence would be]
Probability:      [1–5]  1=Rare  3=Possible  5=Almost certain
Impact:           [1–5]  1=Negligible  3=Significant  5=Critical
Risk Score:       [P × I = score]
Rating:           [LOW 1–6 / MEDIUM 7–12 / HIGH 13–19 / CRITICAL 20–25]
Owner:            [name / role]
Status:           [OPEN / MITIGATING / ESCALATED / CLOSED]
Identified:       [date]
Last reviewed:    [date]

Mitigation action: [what is being done to reduce probability or impact]
Residual score after mitigation: [P × I]
Contingency (if risk materialises): [pre-agreed response]
Early warning indicators: [what to watch for]

Risk Scoring Matrix

Impact 1Impact 2Impact 3Impact 4Impact 5
Prob 55 MED10 MED15 HIGH20 CRIT25 CRIT
Prob 44 LOW8 MED12 MED16 HIGH20 CRIT
Prob 33 LOW6 MED9 MED12 MED15 HIGH
Prob 22 LOW4 LOW6 MED8 MED10 MED
Prob 11 LOW2 LOW3 LOW4 LOW5 MED

Escalation thresholds:

  • CRITICAL (20–25): Escalate to [PM] immediately. Client notification required.
  • HIGH (13–19): Mitigation plan required within 48 hours. Review weekly.
  • MEDIUM (7–12): Mitigation plan required. Review monthly.
  • LOW (1–6): Monitor. Review at milestone.

Initial Risk Register (Civil Project Template)

Seed these risks at project start. Score and assign for each project:

IDDescriptionCategoryDefault Probability
R-001Ground conditions worse than anticipatedTECHNICAL3
R-002Design changes during constructionTECHNICAL3
R-003Contractor programme delayPROGRAMME3
R-004Material price escalationCOMMERCIAL2
R-005Client payment delayCOMMERCIAL3
R-006Regulatory approval delayREGULATORY2
R-007Scope increase not captured as variationCOMMERCIAL3
R-008HSE incident on siteHSE2
R-009Key personnel unavailabilityPROGRAMME2
R-010Third-party utility clashTECHNICAL2

Risk Review Protocol

At each reporting cycle:

  1. Review all OPEN risks — update probability, impact, mitigation status
  2. Check early warning indicators for HIGH and CRITICAL risks
  3. Close any risks that are no longer applicable
  4. Add any new risks identified this period
  5. Flag any risk that has escalated in score since last review

Output a risk summary for inclusion in report:

RISK SUMMARY FOR REPORT:
  Total open risks: [N]
  CRITICAL: [N]  HIGH: [N]  MEDIUM: [N]  LOW: [N]
  New this period: [N]
  Closed this period: [N]
  Top 3 risks: [R-ID, description, score, mitigation status]

示例提示词

发现了一个新的进度风险,帮我更新一下风险登记册。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

项目风险登记管理能做什么?

Manages the full civil-engineering risk lifecycle: identify, score, assign, mitigate, monitor, escalate, and close. Use for risk identification, updates, or risk register review。

如何安装项目风险登记管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「项目风险登记管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

项目风险登记管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

项目风险登记管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。