Manages the full civil-engineering risk lifecycle: identify, score, assign, mitigate, monitor, escalate, and close. Use for risk identification, updates, or risk register review.
SKILL.md
PM Risk
Risk register management for civil engineering projects. Full lifecycle: identify → score → assign → mitigate → monitor → escalate → close.
Risk Register Format
Each risk record:
RISK RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID: R-[NNN]
Category: [TECHNICAL / COMMERCIAL / PROGRAMME / HSE / REGULATORY / EXTERNAL]
Description: [what could happen and what the consequence would be]
Probability: [1–5] 1=Rare 3=Possible 5=Almost certain
Impact: [1–5] 1=Negligible 3=Significant 5=Critical
Risk Score: [P × I = score]
Rating: [LOW 1–6 / MEDIUM 7–12 / HIGH 13–19 / CRITICAL 20–25]
Owner: [name / role]
Status: [OPEN / MITIGATING / ESCALATED / CLOSED]
Identified: [date]
Last reviewed: [date]
Mitigation action: [what is being done to reduce probability or impact]
Residual score after mitigation: [P × I]
Contingency (if risk materialises): [pre-agreed response]
Early warning indicators: [what to watch for]
Risk Scoring Matrix
| Impact 1 | Impact 2 | Impact 3 | Impact 4 | Impact 5 | |
|---|---|---|---|---|---|
| Prob 5 | 5 MED | 10 MED | 15 HIGH | 20 CRIT | 25 CRIT |
| Prob 4 | 4 LOW | 8 MED | 12 MED | 16 HIGH | 20 CRIT |
| Prob 3 | 3 LOW | 6 MED | 9 MED | 12 MED | 15 HIGH |
| Prob 2 | 2 LOW | 4 LOW | 6 MED | 8 MED | 10 MED |
| Prob 1 | 1 LOW | 2 LOW | 3 LOW | 4 LOW | 5 MED |
Escalation thresholds:
- CRITICAL (20–25): Escalate to [PM] immediately. Client notification required.
- HIGH (13–19): Mitigation plan required within 48 hours. Review weekly.
- MEDIUM (7–12): Mitigation plan required. Review monthly.
- LOW (1–6): Monitor. Review at milestone.
Initial Risk Register (Civil Project Template)
Seed these risks at project start. Score and assign for each project:
| ID | Description | Category | Default Probability |
|---|---|---|---|
| R-001 | Ground conditions worse than anticipated | TECHNICAL | 3 |
| R-002 | Design changes during construction | TECHNICAL | 3 |
| R-003 | Contractor programme delay | PROGRAMME | 3 |
| R-004 | Material price escalation | COMMERCIAL | 2 |
| R-005 | Client payment delay | COMMERCIAL | 3 |
| R-006 | Regulatory approval delay | REGULATORY | 2 |
| R-007 | Scope increase not captured as variation | COMMERCIAL | 3 |
| R-008 | HSE incident on site | HSE | 2 |
| R-009 | Key personnel unavailability | PROGRAMME | 2 |
| R-010 | Third-party utility clash | TECHNICAL | 2 |
Risk Review Protocol
At each reporting cycle:
- Review all OPEN risks — update probability, impact, mitigation status
- Check early warning indicators for HIGH and CRITICAL risks
- Close any risks that are no longer applicable
- Add any new risks identified this period
- Flag any risk that has escalated in score since last review
Output a risk summary for inclusion in report:
RISK SUMMARY FOR REPORT:
Total open risks: [N]
CRITICAL: [N] HIGH: [N] MEDIUM: [N] LOW: [N]
New this period: [N]
Closed this period: [N]
Top 3 risks: [R-ID, description, score, mitigation status]
示例提示词
发现了一个新的进度风险,帮我更新一下风险登记册。
所属插件
安装该插件会一并获得同领域的 44 个 Skill / MCP。
同插件的其他科研 Skill
- 建筑图纸矢量生成Produces coordinated architectural drawings (plans, sections, elevations, SVG/DXF) from structured specs with layer and standard checks. Use when drafting or generating drawing sets.
- 建筑项目全流程协调Coordinates end-to-end AEC work across briefing, design, BIM/CAD production, and handover by routing to specialist skills. Use for ambiguous or multi-discipline AEC tasks.
- 建筑任务书空间排布Converts briefs into traceable room programs, area schedules, adjacency logic, and requirement matrices. Use for space planning, briefing, or program validation.
- 建筑成果红队复核Independently challenges an architecture deliverable for hidden assumptions, coordination gaps, and unsupported claims before submission. Use for final adversarial review before issue.
- 建筑面积工程量核算Calculates and audits architectural areas, room schedules, quantities, and takeoffs with explicit units and measurement basis. Use for quantity reconciliation and takeoff sanity checks.
- AutoCAD DWG制图工作流Plans and reviews safe AutoCAD DWG workflows: layers, blocks, xrefs, layouts, plotting, and AutoLISP/.NET automation. Use for AutoCAD-specific drafting and DWG package preparation.
- BIM执行计划编制Drafts and reviews ISO 19650 BIM Execution Plans and Exchange Information Requirements: roles, CDE workflow, LOIN, and federation strategy. Use before modeling starts on a BIM-delivered project.
- 建筑围护结构性能设计Develops and reviews facade, roof, and foundation envelope strategies for thermal, water, air, and acoustic performance. Use for assembly design, condensation risk, and envelope QA.
- CAD/BIM自动化工作流Plans safe, least-destructive automation of CAD/BIM workflows such as batch edits and model-data extraction across Revit, IFC, DWG, and DXF. Use for repetitive model or document tasks.
- 建筑场地土木协调Coordinates architecture with civil/site engineering: grading, earthworks, access, drainage, utilities, and Civil 3D workflows. Use for site grading concepts and civil-architectural handoff.
- 建筑概念方案评审Critiques architectural concepts and compares design options against stated project goals across program, site, climate, and constructability. Use for design critique or option comparison.
- 建筑概念与方案设计Generates and develops concept and schematic design options (parti, massing, blocking, circulation, floor plans) from a validated brief. Use for early design option generation and comparison.
- 施工阶段行政管理支持Supports construction-phase administration: RFIs, submittals, site observations, change tracking, and punch lists. Use during tender clarification, construction, and closeout.
- 施工图文件集编制Develops and coordinates construction-document sets including sheet registers, schedules, details, and issue packages. Use for technical design production and permit or tender drawing sets.
- 土木项目成本管理Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review.
- 建筑造价与价值工程Supports architectural cost planning, option comparison, and value engineering using traceable quantities and cost sources. Use for early cost plans, budget reconciliation, and VE workshops.
- 项目文件发布核查Audits live civil-engineering project documents after a milestone to flag drift between proposed, contracted, and delivered work. Use after report issue or scope change to update project records.
- 建筑图纸质量检查QA checks architectural drawing sets for cross-sheet coordination, annotation, dimension, and revision issues. Use for reviewing PDFs, exported drawings, or issue sets before release.
- 岩土勘察与地基评估Plans and interprets geotechnical site investigations for foundation design: desk study, borehole/CPT interpretation, and bearing capacity checks. Use before foundation or earthworks design.
- 竣工移交与运维协调Coordinates architectural handover, O&M manuals, asset data, defects, and post-occupancy evaluation. Use from practical completion through building operation and facilities handoff.
- 历史建筑保护评估Researches heritage significance, listing status, and conservation constraints for existing buildings, and structures conservation-led options. Use for listed or historic buildings.
- 土木项目安全环保管理Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review.
- 室内装修布局设计Develops interior and fit-out layouts, furniture zoning, RCP concepts, finish strategies, and fit-out documentation. Use for workplace, residential, retail, or hospitality interior projects.
- 结构与无损检测根因调查Runs a systematic root-cause investigation protocol for structural and NDT findings before any remediation is proposed. Use when a defect, anomaly, or unexplained inspection finding is reported.
常见问题
项目风险登记管理能做什么?
Manages the full civil-engineering risk lifecycle: identify, score, assign, mitigate, monitor, escalate, and close. Use for risk identification, updates, or risk register review。
如何安装项目风险登记管理?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「项目风险登记管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
项目风险登记管理需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
项目风险登记管理经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。