PM Cost

Budget and cost control for civil engineering projects. Contract sum → variation log → forecast final account → cashflow → invoice register.


Cost Baseline

Establish at contract execution:

COST BASELINE
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Original Contract Sum:        ₦/$ [amount]
Provisional Sums (if any):    ₦/$ [amount]
Contingency (if held by PM):  ₦/$ [amount]  ([N]%)
Total Approved Budget:         ₦/$ [amount]

Breakdown by WBS (if BOQ available):
  2.0 Civil/Structural:  ₦/$ [amount]  ([N]%)
  3.0 Architectural:     ₦/$ [amount]  ([N]%)
  4.0 MEP:               ₦/$ [amount]  ([N]%)
  1.0 PM / Prelims:      ₦/$ [amount]  ([N]%)
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Variation Log

Every scope change, instruction, or claim is logged before pricing:

VARIATION RECORD
  ID:             VAR-[NNN]
  Date raised:    [date]
  Raised by:      [client / the firm / contractor / site condition]
  Description:    [what changed]
  Type:           [ADDITION / OMISSION / SUBSTITUTION / ACCELERATION]
  Entitlement:    [AGREED / DISPUTED / UNDER REVIEW]
  Pricing basis:  [BOQ rates / dayworks / lump sum agreement / TBD]
  Estimated value: ₦/$ [amount]
  Agreed value:    ₦/$ [amount or TBD]
  Variation order ref: [VO-NNN or VERBAL — pending VO]
  Status:         [OPEN / PRICED / AGREED / INCORPORATED / DISPUTED]

Alert: Any variation performed without a signed variation order is a commercial risk. Flag immediately and pursue written confirmation. Flag for [PM] sign-off before proceeding if required by the contract.


Forecast Final Account

Update at each reporting period:

FORECAST FINAL ACCOUNT
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Original Contract Sum:              ₦/$ [amount]
Agreed Variations to date:    +/−  ₦/$ [amount]
Pending Variations (estimated):    ₦/$ [amount]
Provisional Sums instructed:       ₦/$ [amount]
FORECAST FINAL ACCOUNT:             ₦/$ [amount]

Variance from original:        +/− ₦/$ [amount]  ([N]%)
Contingency remaining:              ₦/$ [amount]
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Escalation threshold: If forecast final account exceeds original contract sum by >10% → notify client, route to report.


Invoice Register

Track all invoices:

Inv NoRefDate IssuedAmountPayment TermsDue DateDate PaidOutstandingStatus
INV-001PRJ/INV/YYYY/001₦/$30 daysPAID/OUTSTANDING/OVERDUE

Payment monitoring:

  • 7 days before due: reminder
  • On due date unpaid: flag in orchestrator proactive alerts
  • 14 days overdue: escalate to [PM] — formal demand
  • 30 days overdue: route to [PM] — consider suspension of services per contract

Cashflow Forecast

Monthly cashflow projection:

CASHFLOW FORECAST
Month | Planned Expenditure | Planned Invoice | Forecast Receipt
[month] | ₦/$ | ₦/$ | ₦/$

Flag any month where receipts are projected to fall below expenditure — cashflow risk to the firm operations.


Cost Report Summary (for report)

COST SUMMARY FOR REPORT:
  Original contract sum:      ₦/$ [amount]
  Approved variations:        ₦/$ [amount]
  Forecast final account:     ₦/$ [amount]
  Variance:                   [+N% / −N%]
  Contingency consumed:       [N]%
  Invoiced to date:           ₦/$ [amount]  ([N]% of forecast)
  Collected to date:          ₦/$ [amount]
  Outstanding invoices:       ₦/$ [amount]
  Top cost risk this period:  [VAR-ID or risk description]

示例提示词

收到一份变更指令,帮我更新项目的合同总价和现金流预测。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

土木项目成本管理能做什么?

Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review。

如何安装土木项目成本管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「土木项目成本管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

土木项目成本管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

土木项目成本管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。