SKILL.md
Investigate
Systematic root cause investigation for structural anomalies, NDT findings,
and inspection defects. Adapted from the gstack /investigate methodology
for civil engineering practice.
IRON LAW: No remediation recommendation, no repair specification, no client communication about fixes — until root cause is confirmed. Treating symptoms creates cascading failures. Every unresolved root cause makes the next finding harder to interpret.
Phase 1 — Symptom Gathering
Before forming any hypothesis, collect all available evidence.
1.1 Physical Observations
Ask for or extract:
- Location, distribution, and pattern of the defect (isolated vs. systematic)
- Dimensions: extent, depth (if measurable), orientation
- Visual characteristics: colour, texture, geometry (e.g. map cracking vs. diagonal shear crack, uniform corrosion vs. pitting)
- Age and progression: when first observed, any change since?
- Environmental context: exposure zone, drainage, loading history
1.2 Drawings and Records Review
Check:
- Original design drawings — specified materials, loadings, details
- As-built record (if available) — deviations from design
- Previous inspection reports — any prior findings at this location?
- Construction records — pour sequence, curing method, weld procedures, NDT certs
- Maintenance history — any prior repairs, coatings, interventions?
1.3 NDT Data Review
Compile available data:
- Rebound hammer readings (carbonation depth, surface hardness)
- Cover meter / rebar scan results
- UPV readings (velocity, signal quality)
- Half-cell potential maps (if corrosion investigation)
- Ultrasonic thickness readings (for steel / tank walls)
- Visual inspection photos
Flag any data gaps at this stage. Do not proceed to hypothesis if critical data is missing — state what additional testing is needed first.
Phase 2 — Prior Investigation Check
Before forming a new hypothesis, check:
- Has this location or element been investigated before?
- Are there recurring findings at this element type across the project or site?
- Recurring defects in the same area are an architectural / construction / design smell — note patterns.
If prior investigation records exist, document:
PRIOR INVESTIGATION NOTE:
Location: [element/zone]
Date of prior investigation: [date]
Prior root cause finding: [summary]
Prior remedy applied: [yes/no, description]
Current status vs. prior: [same / worse / new location]
Phase 3 — Hypothesis Formation
Generate 2–3 candidate hypotheses, ranked by probability based on evidence.
For each hypothesis:
HYPOTHESIS [N]:
Proposed root cause: [mechanism]
Supporting evidence: [list observations that support this]
Contradicting evidence: [list observations that conflict with this]
Probability: [HIGH / MEDIUM / LOW]
Distinguishing test: [what single test would confirm or rule this out]
Common Root Cause Categories by Domain
Reinforced Concrete — Cracking:
- Structural overload (flexure, shear, torsion)
- Differential settlement
- Thermal/shrinkage during curing
- Corrosion-induced expansion (follow with half-cell potential)
- Alkali-silica reaction (map cracking, gel exudation)
- Carbonation-induced depassivation
Reinforced Concrete — Delamination / Spalling:
- Corrosion of rebar (insufficient cover, chloride ingress, carbonation)
- Freeze-thaw cycling
- Fire damage
- Impact / mechanical damage
Steel Structures — Corrosion:
- General atmospheric corrosion (coating failure)
- Galvanic corrosion (dissimilar metals in contact)
- Crevice corrosion (trapped moisture)
- Stress corrosion cracking (high-tensile members under sustained load)
- MIC (microbiologically influenced — offshore / subsea)
Foundation — Settlement:
- Consolidation of compressible layer (differential if variable soil)
- Loss of bearing capacity (scour, piping, erosion)
- Expansive / collapsible soils
- Vibration-induced densification
- Inadequate founding depth
Welds — Defects:
- Lack of fusion (wrong technique, dirty joint, wrong current)
- Porosity (moisture contamination, wrong shielding gas, wrong electrode)
- Undercut (excessive current, wrong angle)
- Hot cracking (high restraint, wrong preheat)
- Hydrogen-induced cracking (wrong preheat, high-strength steel)
Tank / Vessel — Calibration Anomaly:
- Strapping measurement error (check key dimensions)
- Shell deformation (dents, bulges outside tolerance)
- Floating roof seal displacement
- Product level gauge calibration drift
Phase 4 — Test Protocol
For the highest-probability hypothesis, specify the minimum test needed to confirm or refute it. Do not over-specify — one well-chosen test first.
PROPOSED INVESTIGATION TEST:
Hypothesis being tested: [N]
Test method: [specific NDT method, standard, equipment]
Location: [exact element / grid / zone]
Pass/fail criterion: [what result confirms the hypothesis]
Estimated duration: [field time]
Additional resource needed: [equipment, access, specialist]
If the test result confirms the hypothesis → proceed to Phase 5. If the test result refutes the hypothesis → return to Phase 3, demote this hypothesis, promote the next.
THREE-STRIKE RULE: If three consecutive hypotheses are tested and refuted, STOP. Do not continue guessing. The anomaly requires a broader investigation scope — escalate to:
- Specialist consultant (geotechnical, materials lab, structural analyst)
- Destructive investigation (core sample, trial pit, cut-out)
- Document the three failed hypotheses as evidence for the scope escalation
Phase 5 — Root Cause Confirmation
When a hypothesis is confirmed by test evidence, document:
ROOT CAUSE CONFIRMED:
Mechanism: [specific failure mechanism]
Primary cause: [design deficiency / construction defect / material failure /
environmental / operational / maintenance gap]
Contributing factors: [list secondary causes]
Extent: [localised / systematic / progressive]
Urgency: [IMMEDIATE / SHORT-TERM / MONITOR]
Urgency Classification
| Class | Criteria | Action |
|---|---|---|
| IMMEDIATE | Structural capacity compromised, life safety risk | Restrict access, emergency prop/shore, notify client same day |
| SHORT-TERM | Defect is progressing, will reach structural threshold within one inspection cycle | Remediation within agreed programme |
| MONITOR | Defect is stable, no immediate risk | Inspect at defined interval, set trigger threshold |
Phase 6 — Remediation Scoping (Post-Confirmation Only)
Only after root cause is confirmed:
- Specify the remediation objective (restore capacity, arrest progression, seal, replace)
- Reference applicable standard for the repair (ACI 224.1R, EN 1504, API 653 Annex B, AWS D1.1 etc.)
- Identify any design input required before repair specification
- List any regulatory notification obligations ([National Regulator], client HSEMS, insurance)
Output Format
Every investigation session concludes with a structured finding note:
PM INVESTIGATION NOTE
Ref: PRJ/INV/[YYYY]/[NNN]
Date: [date]
Project: [project name / client]
Element: [structural element / zone]
SYMPTOM SUMMARY:
[3–5 bullet observations]
HYPOTHESES CONSIDERED:
1. [hypothesis] — [CONFIRMED / REFUTED / UNTESTED]
2. [hypothesis] — [CONFIRMED / REFUTED / UNTESTED]
ROOT CAUSE:
[confirmed mechanism, or "INCONCLUSIVE — escalation required"]
URGENCY: [IMMEDIATE / SHORT-TERM / MONITOR]
RECOMMENDED NEXT STEP:
[single specific action — test, repair spec, monitor programme, or escalation]
Prepared by: [PM]
This note feeds directly into any subsequent project report or proposal.
示例提示词
检测发现这处裂缝有点异常,帮我做一次根因调查分析。
所属插件
安装该插件会一并获得同领域的 44 个 Skill / MCP。
同插件的其他科研 Skill
- 建筑图纸矢量生成Produces coordinated architectural drawings (plans, sections, elevations, SVG/DXF) from structured specs with layer and standard checks. Use when drafting or generating drawing sets.
- 建筑项目全流程协调Coordinates end-to-end AEC work across briefing, design, BIM/CAD production, and handover by routing to specialist skills. Use for ambiguous or multi-discipline AEC tasks.
- 建筑任务书空间排布Converts briefs into traceable room programs, area schedules, adjacency logic, and requirement matrices. Use for space planning, briefing, or program validation.
- 建筑成果红队复核Independently challenges an architecture deliverable for hidden assumptions, coordination gaps, and unsupported claims before submission. Use for final adversarial review before issue.
- 建筑面积工程量核算Calculates and audits architectural areas, room schedules, quantities, and takeoffs with explicit units and measurement basis. Use for quantity reconciliation and takeoff sanity checks.
- AutoCAD DWG制图工作流Plans and reviews safe AutoCAD DWG workflows: layers, blocks, xrefs, layouts, plotting, and AutoLISP/.NET automation. Use for AutoCAD-specific drafting and DWG package preparation.
- BIM执行计划编制Drafts and reviews ISO 19650 BIM Execution Plans and Exchange Information Requirements: roles, CDE workflow, LOIN, and federation strategy. Use before modeling starts on a BIM-delivered project.
- 建筑围护结构性能设计Develops and reviews facade, roof, and foundation envelope strategies for thermal, water, air, and acoustic performance. Use for assembly design, condensation risk, and envelope QA.
- CAD/BIM自动化工作流Plans safe, least-destructive automation of CAD/BIM workflows such as batch edits and model-data extraction across Revit, IFC, DWG, and DXF. Use for repetitive model or document tasks.
- 建筑场地土木协调Coordinates architecture with civil/site engineering: grading, earthworks, access, drainage, utilities, and Civil 3D workflows. Use for site grading concepts and civil-architectural handoff.
- 建筑概念方案评审Critiques architectural concepts and compares design options against stated project goals across program, site, climate, and constructability. Use for design critique or option comparison.
- 建筑概念与方案设计Generates and develops concept and schematic design options (parti, massing, blocking, circulation, floor plans) from a validated brief. Use for early design option generation and comparison.
- 施工阶段行政管理支持Supports construction-phase administration: RFIs, submittals, site observations, change tracking, and punch lists. Use during tender clarification, construction, and closeout.
- 施工图文件集编制Develops and coordinates construction-document sets including sheet registers, schedules, details, and issue packages. Use for technical design production and permit or tender drawing sets.
- 土木项目成本管理Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review.
- 建筑造价与价值工程Supports architectural cost planning, option comparison, and value engineering using traceable quantities and cost sources. Use for early cost plans, budget reconciliation, and VE workshops.
- 项目文件发布核查Audits live civil-engineering project documents after a milestone to flag drift between proposed, contracted, and delivered work. Use after report issue or scope change to update project records.
- 建筑图纸质量检查QA checks architectural drawing sets for cross-sheet coordination, annotation, dimension, and revision issues. Use for reviewing PDFs, exported drawings, or issue sets before release.
- 岩土勘察与地基评估Plans and interprets geotechnical site investigations for foundation design: desk study, borehole/CPT interpretation, and bearing capacity checks. Use before foundation or earthworks design.
- 竣工移交与运维协调Coordinates architectural handover, O&M manuals, asset data, defects, and post-occupancy evaluation. Use from practical completion through building operation and facilities handoff.
- 历史建筑保护评估Researches heritage significance, listing status, and conservation constraints for existing buildings, and structures conservation-led options. Use for listed or historic buildings.
- 土木项目安全环保管理Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review.
- 室内装修布局设计Develops interior and fit-out layouts, furniture zoning, RCP concepts, finish strategies, and fit-out documentation. Use for workplace, residential, retail, or hospitality interior projects.
- 建筑生命安全与无障碍设计Coordinates life-safety and accessibility design using jurisdiction-specific requirements: egress, fire compartmentation, and accessible routes. Use for code-review matrices and egress studies.
常见问题
结构与无损检测根因调查能做什么?
Runs a systematic root-cause investigation protocol for structural and NDT findings before any remediation is proposed. Use when a defect, anomaly, or unexplained inspection finding is reported。
如何安装结构与无损检测根因调查?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「结构与无损检测根因调查」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
结构与无损检测根因调查需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
结构与无损检测根因调查经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。