hse
Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review.
SKILL.md
PM HSE
Health, safety, and environment management for civil engineering projects. Safety plan → method statement review → incident management → statutory reporting.
RULE: Any incident with injury, fatality, or environmental release is an IMMEDIATE escalation to [PM]. No communication to regulators or client before [PM] has reviewed the facts.
HSE Plan Essentials
Set up at project start. Minimum required elements:
| Element | Status |
|---|---|
| Project HSE Plan (site-specific) | [ ] Prepared / [ ] Client approved |
| Emergency Response Plan | [ ] Prepared |
| Site-specific risk assessment | [ ] Prepared |
| First Aid provisions confirmed | [ ] |
| PPE requirements defined | [ ] |
| Site induction programme | [ ] Prepared |
| Method statements for high-risk activities | [ ] Identified / [ ] Prepared |
| Environmental controls (waste, water, noise) | [ ] Identified |
| Regulatory notifications (if applicable) | [ ] Filed |
High-Risk Activity Method Statements
These activities require a written Method Statement and Risk Assessment (MSRA) before work commences. Flag any that apply to this project:
- Excavation > 1.2m depth
- Formwork and falsework
- Working at height (> 2m)
- Crane and lifting operations
- Confined space entry
- Demolition works
- Electrical isolation (LV or HV)
- Hot work (welding, cutting, grinding)
- Hazardous materials handling (asbestos, lead paint, fuel)
- Piling operations
For each applicable activity:
MSRA RECORD
Activity: [description]
MSRA prepared: [yes/no — date]
MSRA reviewed by PM: [yes/no — date]
MSRA approved by client: [yes/no — date, if required]
Toolbox talk conducted: [yes/no — date, attendees]
Permit to work required: [yes/no — permit type]
Incident Classification
| Class | Description | Immediate action |
|---|---|---|
| FATALITY | Death on site or caused by site activity | STOP ALL WORK. [PM] + client within 1 hour. Regulator within 24 hours. Preserve scene. |
| SERIOUS INJURY | Lost time injury, hospitalisation, permanent disability | STOP affected work. [PM] + client same day. Regulator as required. |
| MINOR INJURY | First aid treatment, no lost time | First aid administered, logged, reported to site manager |
| NEAR-MISS | Potential for injury but no injury occurred | Investigate within 24 hours — near-misses predict future incidents |
| UNSAFE CONDITION | Hazard identified before incident | Correct immediately or isolate. Log and report. |
| ENVIRONMENTAL | Spill, discharge, noise/dust exceedance | Contain, report to PM, notify client and regulator as required |
Incident Record
INCIDENT RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID: INC-[NNN]
Date/time: [date and time]
Location: [WBS ref + physical description]
Class: [FATALITY / SERIOUS INJURY / MINOR INJURY / NEAR-MISS /
UNSAFE CONDITION / ENVIRONMENTAL]
Persons involved: [name, role, contractor — anonymise for external reports]
Description: [what happened — factual, no blame language]
Immediate action taken: [first aid, area isolated, equipment stopped, etc.]
Root cause investigation:
Route to investigate for all SERIOUS INJURY, FATALITY, and NEAR-MISS
Contributing factors: [after investigation]
Corrective action: [specific, owner, date]
Preventive action: [systemic change to prevent recurrence]
Statutory reporting required: [yes/no — which body — deadline]
Client notification required: [yes/no — deadline]
Reported by: [name]
Report date: [date]
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
Statutory Reporting (Nigeria context)
| Event | Reporting body | Timeline |
|---|---|---|
| Fatality | [National Regulator] (if oil & gas) / State OSHE agency | 24 hours |
| Serious injury (hospitalisation) | Employer / insurance / state agency | 7 days |
| Environmental release (oil & gas) | [National Regulator] / NOSDRA | Immediate notification |
| Environmental release (civil) | NESREA / state EPA | 24 hours |
| Structural collapse | COREN / state regulator | 24 hours |
Require explicit [PM] sign-off before any statutory notification is submitted.
Toolbox Talk Register
Weekly minimum. Log:
| Date | Topic | Conducted by | Attendees (N) | Sign-off sheet filed |
|---|
HSE Summary (for report)
HSE SUMMARY FOR REPORT:
Incidents this period: FATALITY [N] SERIOUS [N] MINOR [N]
Near-misses this period: [N]
Unsafe conditions reported: [N resolved / N open]
Lost Time Injury (LTI): [N]
LTI Frequency Rate (LTIFR): [if tracked — (LTIs × 200,000) / man-hours]
Toolbox talks conducted: [N]
Method statements approved: [N]
Open HSE actions: [N]
示例提示词
现场发生了一起未遂事故,帮我记录并更新安全管理台账。
所属插件
安装该插件会一并获得同领域的 44 个 Skill / MCP。
同插件的其他科研 Skill
- 建筑图纸矢量生成Produces coordinated architectural drawings (plans, sections, elevations, SVG/DXF) from structured specs with layer and standard checks. Use when drafting or generating drawing sets.
- 建筑项目全流程协调Coordinates end-to-end AEC work across briefing, design, BIM/CAD production, and handover by routing to specialist skills. Use for ambiguous or multi-discipline AEC tasks.
- 建筑任务书空间排布Converts briefs into traceable room programs, area schedules, adjacency logic, and requirement matrices. Use for space planning, briefing, or program validation.
- 建筑成果红队复核Independently challenges an architecture deliverable for hidden assumptions, coordination gaps, and unsupported claims before submission. Use for final adversarial review before issue.
- 建筑面积工程量核算Calculates and audits architectural areas, room schedules, quantities, and takeoffs with explicit units and measurement basis. Use for quantity reconciliation and takeoff sanity checks.
- AutoCAD DWG制图工作流Plans and reviews safe AutoCAD DWG workflows: layers, blocks, xrefs, layouts, plotting, and AutoLISP/.NET automation. Use for AutoCAD-specific drafting and DWG package preparation.
- BIM执行计划编制Drafts and reviews ISO 19650 BIM Execution Plans and Exchange Information Requirements: roles, CDE workflow, LOIN, and federation strategy. Use before modeling starts on a BIM-delivered project.
- 建筑围护结构性能设计Develops and reviews facade, roof, and foundation envelope strategies for thermal, water, air, and acoustic performance. Use for assembly design, condensation risk, and envelope QA.
- CAD/BIM自动化工作流Plans safe, least-destructive automation of CAD/BIM workflows such as batch edits and model-data extraction across Revit, IFC, DWG, and DXF. Use for repetitive model or document tasks.
- 建筑场地土木协调Coordinates architecture with civil/site engineering: grading, earthworks, access, drainage, utilities, and Civil 3D workflows. Use for site grading concepts and civil-architectural handoff.
- 建筑概念方案评审Critiques architectural concepts and compares design options against stated project goals across program, site, climate, and constructability. Use for design critique or option comparison.
- 建筑概念与方案设计Generates and develops concept and schematic design options (parti, massing, blocking, circulation, floor plans) from a validated brief. Use for early design option generation and comparison.
- 施工阶段行政管理支持Supports construction-phase administration: RFIs, submittals, site observations, change tracking, and punch lists. Use during tender clarification, construction, and closeout.
- 施工图文件集编制Develops and coordinates construction-document sets including sheet registers, schedules, details, and issue packages. Use for technical design production and permit or tender drawing sets.
- 土木项目成本管理Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review.
- 建筑造价与价值工程Supports architectural cost planning, option comparison, and value engineering using traceable quantities and cost sources. Use for early cost plans, budget reconciliation, and VE workshops.
- 项目文件发布核查Audits live civil-engineering project documents after a milestone to flag drift between proposed, contracted, and delivered work. Use after report issue or scope change to update project records.
- 建筑图纸质量检查QA checks architectural drawing sets for cross-sheet coordination, annotation, dimension, and revision issues. Use for reviewing PDFs, exported drawings, or issue sets before release.
- 岩土勘察与地基评估Plans and interprets geotechnical site investigations for foundation design: desk study, borehole/CPT interpretation, and bearing capacity checks. Use before foundation or earthworks design.
- 竣工移交与运维协调Coordinates architectural handover, O&M manuals, asset data, defects, and post-occupancy evaluation. Use from practical completion through building operation and facilities handoff.
- 历史建筑保护评估Researches heritage significance, listing status, and conservation constraints for existing buildings, and structures conservation-led options. Use for listed or historic buildings.
- 室内装修布局设计Develops interior and fit-out layouts, furniture zoning, RCP concepts, finish strategies, and fit-out documentation. Use for workplace, residential, retail, or hospitality interior projects.
- 结构与无损检测根因调查Runs a systematic root-cause investigation protocol for structural and NDT findings before any remediation is proposed. Use when a defect, anomaly, or unexplained inspection finding is reported.
- 建筑生命安全与无障碍设计Coordinates life-safety and accessibility design using jurisdiction-specific requirements: egress, fire compartmentation, and accessible routes. Use for code-review matrices and egress studies.
常见问题
土木项目安全环保管理能做什么?
Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review。
如何安装土木项目安全环保管理?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「土木项目安全环保管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
土木项目安全环保管理需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
土木项目安全环保管理经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。