RFI与送审管理

rfi

Manages RFI and submittal workflows: opening, routing, tracking, and escalating overdue design queries. Use when a design query, drawing discrepancy, or submittal needs review and approval.

发布者 Codar安全审核通过v0.1.0更新于 2026-11-18

SKILL.md

PM RFI

Request for Information and submittal management. Open → route → track → escalate → close.


When to Raise an RFI

Raise an RFI when:

  • A drawing is missing information required for construction
  • Two drawings or specifications conflict
  • Site conditions differ from design assumptions
  • Contractor needs clarification before proceeding
  • A design change is required due to site finding or client instruction
  • An NCR has a potential design cause (route from quality)
  • A site anomaly requires design input (route from investigate)

Rule: Never instruct a contractor to proceed on the basis of a verbal design clarification. Open an RFI first. The RFI creates the paper trail.


RFI Record

RFI RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID:               RFI-[NNN]
Date raised:      [date]
Raised by:        [contractor / PM / [PM]]
Priority:         [URGENT — work stopped / NORMAL / LOW]
  Urgent: response required within [N] days — state contractual deadline
  Normal: response required within [N] days per contract

Description:
  Drawing / spec ref: [document number and revision]
  Location: [WBS ref + physical location]
  Question: [specific, one question per RFI — split multi-questions]

Attachments:
  [ ] Sketch / photo
  [ ] Extract from drawing
  [ ] Contractor's proposed solution (if any)

Routed to:        [designer / structural engineer / client / specialist]
Date routed:      [date]
Response due:     [date — per contract or agreed]

Response received: [date]
Response ref:      [document number]
Response summary:  [what was decided]

Contractual implication:
  [ ] No impact
  [ ] Variation likely — route to cost
  [ ] Extension of time likely — route to programme
  [ ] Design change — update drawing register

Closed by: [name]
Close date: [date]
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

RFI Register

Track all RFIs in a register. Surface overdue items to orchestrator:

RFI-IDDate raisedPriorityRouted toResponse dueDays outstandingStatus
RFI-001URGENTDesignerOPEN

Overdue thresholds (flag to orchestrator):

  • URGENT: overdue by 1 day → 🔴 IMMEDIATE alert
  • NORMAL: overdue by 3 days → 🟡 THIS WEEK alert
  • LOW: overdue by 7 days → 🔵 LOG alert

Late Response — Contractual Implications

When a designer or client response is late:

  1. Day 1 overdue: Issue a reminder (route via report COM log)
  2. Day 3 overdue (NORMAL) / Day 1 (URGENT): Formal notice of delay to the responding party — this creates the paper trail for any EOT claim
  3. Day 7 overdue: Notify [PM] — consider whether the contractor is entitled to claim extension of time or additional cost due to late information
  4. Work stopped due to late RFI: Immediately notify client and route to programme for delay analysis
LATE RFI NOTICE
Ref: [COM-ID]
To: [designer / client]
Re: RFI-[NNN] — [description]

This RFI was issued on [date] with a required response date of [date].
As at [today's date], no response has been received. The contractor
[is / is not] currently stopped pending this response.

Please provide your response urgently. Continued delay may result in
an extension of time claim and/or additional cost claim by the contractor,
for which [client / employer] may be liable.

Prepared by: [PM]

Drawing Register

Maintain a live register of current drawing revisions:

Drawing NoTitleCurrent RevDateStatusSuperseded Rev
S-001Foundation PlanRev CAFCRev B

AFC = Approved for Construction. Only AFC drawings may be used on site. When a revised drawing is issued, immediately notify site and confirm old revision is withdrawn. Any NCR caused by use of a superseded drawing is a site management failure — log in quality.


RFI Summary (for report)

RFI SUMMARY FOR REPORT:
  RFIs raised this period:    [N]
  RFIs closed this period:    [N]
  Total open RFIs:            [N]
  Overdue RFIs:               [N] — oldest [N days]
  RFIs with EOT implication:  [N]
  RFIs with cost implication: [N]

示例提示词

设计图纸有个疑问,帮我起草一条RFI并跟踪审批流程。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

RFI与送审管理能做什么?

Manages RFI and submittal workflows: opening, routing, tracking, and escalating overdue design queries. Use when a design query, drawing discrepancy, or submittal needs review and approval。

如何安装RFI与送审管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「RFI与送审管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

RFI与送审管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

RFI与送审管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。