Manages RFI and submittal workflows: opening, routing, tracking, and escalating overdue design queries. Use when a design query, drawing discrepancy, or submittal needs review and approval.
SKILL.md
PM RFI
Request for Information and submittal management. Open → route → track → escalate → close.
When to Raise an RFI
Raise an RFI when:
- A drawing is missing information required for construction
- Two drawings or specifications conflict
- Site conditions differ from design assumptions
- Contractor needs clarification before proceeding
- A design change is required due to site finding or client instruction
- An NCR has a potential design cause (route from
quality) - A site anomaly requires design input (route from
investigate)
Rule: Never instruct a contractor to proceed on the basis of a verbal design clarification. Open an RFI first. The RFI creates the paper trail.
RFI Record
RFI RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID: RFI-[NNN]
Date raised: [date]
Raised by: [contractor / PM / [PM]]
Priority: [URGENT — work stopped / NORMAL / LOW]
Urgent: response required within [N] days — state contractual deadline
Normal: response required within [N] days per contract
Description:
Drawing / spec ref: [document number and revision]
Location: [WBS ref + physical location]
Question: [specific, one question per RFI — split multi-questions]
Attachments:
[ ] Sketch / photo
[ ] Extract from drawing
[ ] Contractor's proposed solution (if any)
Routed to: [designer / structural engineer / client / specialist]
Date routed: [date]
Response due: [date — per contract or agreed]
Response received: [date]
Response ref: [document number]
Response summary: [what was decided]
Contractual implication:
[ ] No impact
[ ] Variation likely — route to cost
[ ] Extension of time likely — route to programme
[ ] Design change — update drawing register
Closed by: [name]
Close date: [date]
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
RFI Register
Track all RFIs in a register. Surface overdue items to orchestrator:
| RFI-ID | Date raised | Priority | Routed to | Response due | Days outstanding | Status |
|---|---|---|---|---|---|---|
| RFI-001 | URGENT | Designer | OPEN |
Overdue thresholds (flag to orchestrator):
- URGENT: overdue by 1 day → 🔴 IMMEDIATE alert
- NORMAL: overdue by 3 days → 🟡 THIS WEEK alert
- LOW: overdue by 7 days → 🔵 LOG alert
Late Response — Contractual Implications
When a designer or client response is late:
- Day 1 overdue: Issue a reminder (route via
reportCOM log) - Day 3 overdue (NORMAL) / Day 1 (URGENT): Formal notice of delay to the responding party — this creates the paper trail for any EOT claim
- Day 7 overdue: Notify [PM] — consider whether the contractor is entitled to claim extension of time or additional cost due to late information
- Work stopped due to late RFI: Immediately notify client and route
to
programmefor delay analysis
LATE RFI NOTICE
Ref: [COM-ID]
To: [designer / client]
Re: RFI-[NNN] — [description]
This RFI was issued on [date] with a required response date of [date].
As at [today's date], no response has been received. The contractor
[is / is not] currently stopped pending this response.
Please provide your response urgently. Continued delay may result in
an extension of time claim and/or additional cost claim by the contractor,
for which [client / employer] may be liable.
Prepared by: [PM]
Drawing Register
Maintain a live register of current drawing revisions:
| Drawing No | Title | Current Rev | Date | Status | Superseded Rev |
|---|---|---|---|---|---|
| S-001 | Foundation Plan | Rev C | AFC | Rev B |
AFC = Approved for Construction. Only AFC drawings may be used on site.
When a revised drawing is issued, immediately notify site and confirm old
revision is withdrawn. Any NCR caused by use of a superseded drawing is a
site management failure — log in quality.
RFI Summary (for report)
RFI SUMMARY FOR REPORT:
RFIs raised this period: [N]
RFIs closed this period: [N]
Total open RFIs: [N]
Overdue RFIs: [N] — oldest [N days]
RFIs with EOT implication: [N]
RFIs with cost implication: [N]
示例提示词
设计图纸有个疑问,帮我起草一条RFI并跟踪审批流程。
所属插件
安装该插件会一并获得同领域的 44 个 Skill / MCP。
同插件的其他科研 Skill
- 建筑图纸矢量生成Produces coordinated architectural drawings (plans, sections, elevations, SVG/DXF) from structured specs with layer and standard checks. Use when drafting or generating drawing sets.
- 建筑项目全流程协调Coordinates end-to-end AEC work across briefing, design, BIM/CAD production, and handover by routing to specialist skills. Use for ambiguous or multi-discipline AEC tasks.
- 建筑任务书空间排布Converts briefs into traceable room programs, area schedules, adjacency logic, and requirement matrices. Use for space planning, briefing, or program validation.
- 建筑成果红队复核Independently challenges an architecture deliverable for hidden assumptions, coordination gaps, and unsupported claims before submission. Use for final adversarial review before issue.
- 建筑面积工程量核算Calculates and audits architectural areas, room schedules, quantities, and takeoffs with explicit units and measurement basis. Use for quantity reconciliation and takeoff sanity checks.
- AutoCAD DWG制图工作流Plans and reviews safe AutoCAD DWG workflows: layers, blocks, xrefs, layouts, plotting, and AutoLISP/.NET automation. Use for AutoCAD-specific drafting and DWG package preparation.
- BIM执行计划编制Drafts and reviews ISO 19650 BIM Execution Plans and Exchange Information Requirements: roles, CDE workflow, LOIN, and federation strategy. Use before modeling starts on a BIM-delivered project.
- 建筑围护结构性能设计Develops and reviews facade, roof, and foundation envelope strategies for thermal, water, air, and acoustic performance. Use for assembly design, condensation risk, and envelope QA.
- CAD/BIM自动化工作流Plans safe, least-destructive automation of CAD/BIM workflows such as batch edits and model-data extraction across Revit, IFC, DWG, and DXF. Use for repetitive model or document tasks.
- 建筑场地土木协调Coordinates architecture with civil/site engineering: grading, earthworks, access, drainage, utilities, and Civil 3D workflows. Use for site grading concepts and civil-architectural handoff.
- 建筑概念方案评审Critiques architectural concepts and compares design options against stated project goals across program, site, climate, and constructability. Use for design critique or option comparison.
- 建筑概念与方案设计Generates and develops concept and schematic design options (parti, massing, blocking, circulation, floor plans) from a validated brief. Use for early design option generation and comparison.
- 施工阶段行政管理支持Supports construction-phase administration: RFIs, submittals, site observations, change tracking, and punch lists. Use during tender clarification, construction, and closeout.
- 施工图文件集编制Develops and coordinates construction-document sets including sheet registers, schedules, details, and issue packages. Use for technical design production and permit or tender drawing sets.
- 土木项目成本管理Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review.
- 建筑造价与价值工程Supports architectural cost planning, option comparison, and value engineering using traceable quantities and cost sources. Use for early cost plans, budget reconciliation, and VE workshops.
- 项目文件发布核查Audits live civil-engineering project documents after a milestone to flag drift between proposed, contracted, and delivered work. Use after report issue or scope change to update project records.
- 建筑图纸质量检查QA checks architectural drawing sets for cross-sheet coordination, annotation, dimension, and revision issues. Use for reviewing PDFs, exported drawings, or issue sets before release.
- 岩土勘察与地基评估Plans and interprets geotechnical site investigations for foundation design: desk study, borehole/CPT interpretation, and bearing capacity checks. Use before foundation or earthworks design.
- 竣工移交与运维协调Coordinates architectural handover, O&M manuals, asset data, defects, and post-occupancy evaluation. Use from practical completion through building operation and facilities handoff.
- 历史建筑保护评估Researches heritage significance, listing status, and conservation constraints for existing buildings, and structures conservation-led options. Use for listed or historic buildings.
- 土木项目安全环保管理Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review.
- 室内装修布局设计Develops interior and fit-out layouts, furniture zoning, RCP concepts, finish strategies, and fit-out documentation. Use for workplace, residential, retail, or hospitality interior projects.
- 结构与无损检测根因调查Runs a systematic root-cause investigation protocol for structural and NDT findings before any remediation is proposed. Use when a defect, anomaly, or unexplained inspection finding is reported.
常见问题
RFI与送审管理能做什么?
Manages RFI and submittal workflows: opening, routing, tracking, and escalating overdue design queries. Use when a design query, drawing discrepancy, or submittal needs review and approval。
如何安装RFI与送审管理?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「RFI与送审管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
RFI与送审管理需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
RFI与送审管理经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。