PM Report

Stakeholder reporting and communications management. Pulls data from all other PM skills. Produces progress reports, meeting minutes, and formal correspondence.


Report Types

TypeFrequencyAudienceSections
Weekly Progress ReportWeeklyClient PM + site teamProgress, programme, issues, next week plan
Monthly Progress ReportMonthlyClient managementFull: progress, programme, cost, risk, quality, HSE
Site Instruction LogOngoingSite teamAll client and PM instructions issued
Meeting MinutesPer meetingAll attendeesAgenda, discussions, decisions, actions
Formal CorrespondenceAs requiredClient, contractors, regulatorsLetter format, the firm ref number

Monthly Progress Report Structure

Pull from each skill using their summary outputs:

[PROJECT NAME]
MONTHLY PROGRESS REPORT
Report No: [N]
Period: [month/year]
Date: [issue date]
Ref: PRJ/RPT/YYYY/NNN

1. EXECUTIVE SUMMARY
   [3–5 sentences: overall project status, key achievement this period,
   key issue or risk, outlook for next period]
   Overall status: [GREEN — on track / AMBER — at risk / RED — delayed or over budget]

2. PROGRESS THIS PERIOD
   [from programme: % complete, activities completed, milestones achieved]

3. PROGRAMME STATUS
   [from programme: milestone table, critical path status, SPI, delay summary]
   Forecast completion: [date]
   Variance from baseline: [+/− N days]

4. COST STATUS
   [from cost: contract sum, variations, forecast final account, invoices]
   Budget status: [GREEN / AMBER / RED]

5. RISK REGISTER SUMMARY
   [from risk: top 3 risks, new risks, closed risks]

6. QUALITY
   [from quality: hold points, NCRs, material submittals]

7. HEALTH, SAFETY AND ENVIRONMENT
   [from hse: incidents, near-misses, LTI status, toolbox talks]

8. ISSUES AND DECISIONS REQUIRED
   [items requiring client decision or action — numbered, with deadline]

9. PROGRAMME FOR NEXT PERIOD
   [key activities planned for the next reporting period]

10. ATTACHMENTS
    [ ] Updated programme (Gantt)
    [ ] Photograph record
    [ ] Site instruction log
    [ ] NCR register
    [ ] Risk register

Communication Log

Every formal communication in or out is logged:

Com-IDDateDirectionFromToSubjectRefResponse required byResponse received
COM-001INClient[PM]
COM-002OUT[PM]ClientPRJ/LTR/YYYY/001

Rule: Every communication that carries an instruction, a claim, a notice, or a decision must be logged. Verbal instructions must be confirmed in writing within 24 hours.


Action Register

Every meeting, site visit, or communication generates actions:

Act-IDSourceDescriptionOwnerDue dateStatusClosed date
ACT-001Meeting 001[PM]OPEN

Surface all overdue actions in the orchestrator's proactive alerts.


Meeting Minutes Format

MEETING MINUTES
Project: [name]
Meeting: [type — site meeting / progress meeting / design meeting]
Date: [date]
Location: [venue]
Ref: PRJ/MOM/YYYY/NNN

ATTENDEES:
  [Name — Organisation — Role]

AGENDA ITEMS:
  1. [item] — [discussion summary] — [decision if any]
  2. ...

ACTIONS ARISING:
  [ACT-ID] — [description] — [Owner] — [Due date]

NEXT MEETING: [date / TBD]

Prepared by: [PM]
Issued to: [distribution list]

Status Colour Codes

Apply to every report:

ColourMeaning
🟢 GREENOn track — no significant issues
🟡 AMBERAt risk — issues identified, mitigation in place, monitoring required
🔴 REDOff track — client notification required, recovery plan needed

Apply GREEN/AMBER/RED to: overall project, programme, cost, quality, HSE independently. A project can be GREEN on cost and RED on programme.

示例提示词

月底了,帮我按这段时间的进展写一份给业主的月度报告。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

项目汇报与沟通管理能做什么?

Produces civil-engineering stakeholder reports, meeting minutes, and correspondence by pulling summaries from the programme, cost, and quality skills. Use for reporting and action-log management。

如何安装项目汇报与沟通管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「项目汇报与沟通管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

项目汇报与沟通管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

项目汇报与沟通管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。