Produces civil-engineering stakeholder reports, meeting minutes, and correspondence by pulling summaries from the programme, cost, and quality skills. Use for reporting and action-log management.
SKILL.md
PM Report
Stakeholder reporting and communications management. Pulls data from all other PM skills. Produces progress reports, meeting minutes, and formal correspondence.
Report Types
| Type | Frequency | Audience | Sections |
|---|---|---|---|
| Weekly Progress Report | Weekly | Client PM + site team | Progress, programme, issues, next week plan |
| Monthly Progress Report | Monthly | Client management | Full: progress, programme, cost, risk, quality, HSE |
| Site Instruction Log | Ongoing | Site team | All client and PM instructions issued |
| Meeting Minutes | Per meeting | All attendees | Agenda, discussions, decisions, actions |
| Formal Correspondence | As required | Client, contractors, regulators | Letter format, the firm ref number |
Monthly Progress Report Structure
Pull from each skill using their summary outputs:
[PROJECT NAME]
MONTHLY PROGRESS REPORT
Report No: [N]
Period: [month/year]
Date: [issue date]
Ref: PRJ/RPT/YYYY/NNN
1. EXECUTIVE SUMMARY
[3–5 sentences: overall project status, key achievement this period,
key issue or risk, outlook for next period]
Overall status: [GREEN — on track / AMBER — at risk / RED — delayed or over budget]
2. PROGRESS THIS PERIOD
[from programme: % complete, activities completed, milestones achieved]
3. PROGRAMME STATUS
[from programme: milestone table, critical path status, SPI, delay summary]
Forecast completion: [date]
Variance from baseline: [+/− N days]
4. COST STATUS
[from cost: contract sum, variations, forecast final account, invoices]
Budget status: [GREEN / AMBER / RED]
5. RISK REGISTER SUMMARY
[from risk: top 3 risks, new risks, closed risks]
6. QUALITY
[from quality: hold points, NCRs, material submittals]
7. HEALTH, SAFETY AND ENVIRONMENT
[from hse: incidents, near-misses, LTI status, toolbox talks]
8. ISSUES AND DECISIONS REQUIRED
[items requiring client decision or action — numbered, with deadline]
9. PROGRAMME FOR NEXT PERIOD
[key activities planned for the next reporting period]
10. ATTACHMENTS
[ ] Updated programme (Gantt)
[ ] Photograph record
[ ] Site instruction log
[ ] NCR register
[ ] Risk register
Communication Log
Every formal communication in or out is logged:
| Com-ID | Date | Direction | From | To | Subject | Ref | Response required by | Response received |
|---|---|---|---|---|---|---|---|---|
| COM-001 | IN | Client | [PM] | |||||
| COM-002 | OUT | [PM] | Client | PRJ/LTR/YYYY/001 |
Rule: Every communication that carries an instruction, a claim, a notice, or a decision must be logged. Verbal instructions must be confirmed in writing within 24 hours.
Action Register
Every meeting, site visit, or communication generates actions:
| Act-ID | Source | Description | Owner | Due date | Status | Closed date |
|---|---|---|---|---|---|---|
| ACT-001 | Meeting 001 | [PM] | OPEN |
Surface all overdue actions in the orchestrator's proactive alerts.
Meeting Minutes Format
MEETING MINUTES
Project: [name]
Meeting: [type — site meeting / progress meeting / design meeting]
Date: [date]
Location: [venue]
Ref: PRJ/MOM/YYYY/NNN
ATTENDEES:
[Name — Organisation — Role]
AGENDA ITEMS:
1. [item] — [discussion summary] — [decision if any]
2. ...
ACTIONS ARISING:
[ACT-ID] — [description] — [Owner] — [Due date]
NEXT MEETING: [date / TBD]
Prepared by: [PM]
Issued to: [distribution list]
Status Colour Codes
Apply to every report:
| Colour | Meaning |
|---|---|
| 🟢 GREEN | On track — no significant issues |
| 🟡 AMBER | At risk — issues identified, mitigation in place, monitoring required |
| 🔴 RED | Off track — client notification required, recovery plan needed |
Apply GREEN/AMBER/RED to: overall project, programme, cost, quality, HSE independently. A project can be GREEN on cost and RED on programme.
示例提示词
月底了,帮我按这段时间的进展写一份给业主的月度报告。
所属插件
安装该插件会一并获得同领域的 44 个 Skill / MCP。
同插件的其他科研 Skill
- 建筑图纸矢量生成Produces coordinated architectural drawings (plans, sections, elevations, SVG/DXF) from structured specs with layer and standard checks. Use when drafting or generating drawing sets.
- 建筑项目全流程协调Coordinates end-to-end AEC work across briefing, design, BIM/CAD production, and handover by routing to specialist skills. Use for ambiguous or multi-discipline AEC tasks.
- 建筑任务书空间排布Converts briefs into traceable room programs, area schedules, adjacency logic, and requirement matrices. Use for space planning, briefing, or program validation.
- 建筑成果红队复核Independently challenges an architecture deliverable for hidden assumptions, coordination gaps, and unsupported claims before submission. Use for final adversarial review before issue.
- 建筑面积工程量核算Calculates and audits architectural areas, room schedules, quantities, and takeoffs with explicit units and measurement basis. Use for quantity reconciliation and takeoff sanity checks.
- AutoCAD DWG制图工作流Plans and reviews safe AutoCAD DWG workflows: layers, blocks, xrefs, layouts, plotting, and AutoLISP/.NET automation. Use for AutoCAD-specific drafting and DWG package preparation.
- BIM执行计划编制Drafts and reviews ISO 19650 BIM Execution Plans and Exchange Information Requirements: roles, CDE workflow, LOIN, and federation strategy. Use before modeling starts on a BIM-delivered project.
- 建筑围护结构性能设计Develops and reviews facade, roof, and foundation envelope strategies for thermal, water, air, and acoustic performance. Use for assembly design, condensation risk, and envelope QA.
- CAD/BIM自动化工作流Plans safe, least-destructive automation of CAD/BIM workflows such as batch edits and model-data extraction across Revit, IFC, DWG, and DXF. Use for repetitive model or document tasks.
- 建筑场地土木协调Coordinates architecture with civil/site engineering: grading, earthworks, access, drainage, utilities, and Civil 3D workflows. Use for site grading concepts and civil-architectural handoff.
- 建筑概念方案评审Critiques architectural concepts and compares design options against stated project goals across program, site, climate, and constructability. Use for design critique or option comparison.
- 建筑概念与方案设计Generates and develops concept and schematic design options (parti, massing, blocking, circulation, floor plans) from a validated brief. Use for early design option generation and comparison.
- 施工阶段行政管理支持Supports construction-phase administration: RFIs, submittals, site observations, change tracking, and punch lists. Use during tender clarification, construction, and closeout.
- 施工图文件集编制Develops and coordinates construction-document sets including sheet registers, schedules, details, and issue packages. Use for technical design production and permit or tender drawing sets.
- 土木项目成本管理Manages civil-engineering project budgets: contract sum, variation log, forecast final account, cashflow, and invoice register. Use for cost events such as variations, invoices, or budget review.
- 建筑造价与价值工程Supports architectural cost planning, option comparison, and value engineering using traceable quantities and cost sources. Use for early cost plans, budget reconciliation, and VE workshops.
- 项目文件发布核查Audits live civil-engineering project documents after a milestone to flag drift between proposed, contracted, and delivered work. Use after report issue or scope change to update project records.
- 建筑图纸质量检查QA checks architectural drawing sets for cross-sheet coordination, annotation, dimension, and revision issues. Use for reviewing PDFs, exported drawings, or issue sets before release.
- 岩土勘察与地基评估Plans and interprets geotechnical site investigations for foundation design: desk study, borehole/CPT interpretation, and bearing capacity checks. Use before foundation or earthworks design.
- 竣工移交与运维协调Coordinates architectural handover, O&M manuals, asset data, defects, and post-occupancy evaluation. Use from practical completion through building operation and facilities handoff.
- 历史建筑保护评估Researches heritage significance, listing status, and conservation constraints for existing buildings, and structures conservation-led options. Use for listed or historic buildings.
- 土木项目安全环保管理Manages civil-engineering health, safety, and environment: safety plans, incident register, method statement review, and statutory reporting. Use for any HSE incident, near-miss, or safety review.
- 室内装修布局设计Develops interior and fit-out layouts, furniture zoning, RCP concepts, finish strategies, and fit-out documentation. Use for workplace, residential, retail, or hospitality interior projects.
- 结构与无损检测根因调查Runs a systematic root-cause investigation protocol for structural and NDT findings before any remediation is proposed. Use when a defect, anomaly, or unexplained inspection finding is reported.
常见问题
项目汇报与沟通管理能做什么?
Produces civil-engineering stakeholder reports, meeting minutes, and correspondence by pulling summaries from the programme, cost, and quality skills. Use for reporting and action-log management。
如何安装项目汇报与沟通管理?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「项目汇报与沟通管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
项目汇报与沟通管理需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
项目汇报与沟通管理经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。