Manages civil-engineering quality: inspection and test plans, hold points, NCR lifecycle, and material submittal register. Use when an NCR is raised, an inspection fails, or a hold point is reached.

发布者 Codar安全审核通过v0.1.0更新于 2026-11-18

SKILL.md

PM Quality

Quality management for civil engineering projects. ITP → hold points → NCR lifecycle → material submittals → quality audit.


Inspection and Test Plan (ITP)

The ITP defines what gets inspected, by whom, and what the acceptance criterion is. Set up at project start. Standard ITP activities for a civil/structural project:

ActivityInspection typeHold / Witness / ReviewStandardAcceptance criterion
Foundation excavationVisual + level surveyHOLD — client/PM sign-offProject specFormation level, dimensions
Blinding concreteVisual + strengthWITNESSBS 8500 / project specMix design approved, placement observed
Rebar fixingVisual + cover meterHOLD — structural engineerBS 8666 / drawingSize, spacing, cover per drawing
Concrete pour (structural)Visual + cubesWITNESSBS EN 206Mix design, slump, cube results
Concrete cube resultsLab results reviewREVIEWBS EN 12390fck achieved at 28 days
Weld inspectionVisual + NDTHOLD — structural engineerAWS D1.1 / BS EN 1090VT passed, NDT acceptance per standard
WaterproofingVisual + flood testWITNESSProject specNo leaks after 24-hour flood test
Structural completionFull inspectionHOLD — PM + clientDrawing / specPunch list items agreed

HOLD POINT rule: Work cannot proceed past a hold point without a signed-off inspection record. Any hold point requires [PM]'s professional sign-off before work resumes.


Non-Conformance Report (NCR) Lifecycle

When a non-conformance is identified:

NCR RECORD
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━
ID:               NCR-[NNN]
Date raised:      [date]
Raised by:        [PM / client / inspector / QA auditor]
Location:         [WBS ref + physical location]
Description:      [what was found — specific, measurable]
ITP reference:    [which ITP activity this relates to]
Standard breached: [clause reference]
Severity:         [MINOR / MAJOR / CRITICAL]
  Minor — cosmetic or administrative, no structural/safety impact
  Major — non-conforming work requiring corrective action
  Critical — structural or safety implication; STOP WORK on affected area

Proposed disposition:
  [ ] USE AS IS — with justification (requires explicit [PM] sign-off)
  [ ] REPAIR — describe repair method
  [ ] REJECT AND REPLACE — describe scope of removal
  [ ] FURTHER INVESTIGATION — route to investigate

Root cause (required before close):
  [why did this non-conformance occur?]
  Route to investigate if root cause unclear

Corrective action:
  [specific action, owner, due date]

Preventive action:
  [what changes prevent recurrence — process, supervision, materials]

Verification:
  [how will the corrective action be verified?]

Closed by: [name]
Close date: [date]
━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

CRITICAL NCR protocol:

  1. Immediate STOP WORK on affected area
  2. Notify [PM] and obtain explicit sign-off before any instruction issued
  3. Notify client within 24 hours
  4. Root cause investigation before any disposition agreed
  5. Disposition requires [PM] sign-off

Material Submittal Register

Every material used on the project requires an approved submittal before incorporation:

Sub-IDMaterialSubmitted dateSubmitted byReview statusApproved dateNotes
MAT-001Structural concrete mix designContractorUNDER REVIEW / APPROVED / REJECTED
MAT-002Reinforcement steel (mill certs)
MAT-003Structural steel (material certs)
MAT-004Waterproofing membrane
MAT-005Welding consumables (WPS/PQR)

Rule: No material may be incorporated without an approved submittal. Flag any material used without approval — raise NCR.


Quality Summary (for report)

QUALITY SUMMARY FOR REPORT:
  Hold points this period:    [N reached / N signed off / N pending]
  NCRs this period:           [N raised / N closed / N open]
  Open NCRs by severity:      CRITICAL [N]  MAJOR [N]  MINOR [N]
  Oldest open NCR:            [NCR-ID] — [N days open]
  Material submittals:        [N approved / N pending / N rejected]
  Quality audit due:          [date or N/A]

示例提示词

这批材料检验不合格,帮我按质量流程走一下不符合项处理。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

土木项目质量管理能做什么?

Manages civil-engineering quality: inspection and test plans, hold points, NCR lifecycle, and material submittal register. Use when an NCR is raised, an inspection fails, or a hold point is reached。

如何安装土木项目质量管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「土木项目质量管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

土木项目质量管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

土木项目质量管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。