Manages civil-engineering project schedules: WBS, critical path, earned value, and delay analysis in planning and execution modes. Use for milestone updates, delay events, or schedule review.

发布者 Codar安全审核通过v0.1.0更新于 2026-11-18

SKILL.md

PM Programme

Schedule management for civil engineering projects. Baseline → track → analyse → recover.


Work Breakdown Structure (WBS)

Standard WBS for a civil building / infrastructure project. Adapt per project:

Level 1: PROJECT
  Level 2: 1.0 PROJECT MANAGEMENT
    1.1 Project initiation and mobilisation
    1.2 Design management
    1.3 Procurement
    1.4 Reporting and administration
    1.5 Closeout

  Level 2: 2.0 CIVIL AND STRUCTURAL WORKS
    2.1 Site clearance and preparation
    2.2 Earthworks and excavation
    2.3 Foundation works
    2.4 Substructure (basement / ground floor)
    2.5 Superstructure (columns, beams, slabs per floor)
    2.6 Roof structure
    2.7 External works and drainage

  Level 2: 3.0 ARCHITECTURAL WORKS
    3.1 Masonry and blockwork
    3.2 Finishes (floor, wall, ceiling)
    3.3 Doors, windows, ironmongery
    3.4 Waterproofing and roofing

  Level 2: 4.0 MEP WORKS
    4.1 Mechanical
    4.2 Electrical
    4.3 Plumbing and drainage

  Level 2: 5.0 COMMISSIONING AND HANDOVER
    5.1 Testing and commissioning
    5.2 Punch list clearance
    5.3 As-built documentation
    5.4 Practical completion

Milestone Register

Track these key milestones for every project:

IDMilestoneBaseline dateForecast dateActual dateVariance
M-01Notice to Proceed
M-02Design complete / Approved for Construction
M-03Site mobilisation complete
M-04Foundation works complete
M-05Structure to roof level
M-06Watertight / enclosed
M-07MEP rough-in complete
M-08Finishes complete
M-09Commissioning complete
M-10Practical Completion
M-11Final Account agreed

Progress Tracking

Each reporting period, record:

PROGRESS UPDATE
Period: [week/month ending date]

Activity updates:
  [WBS item] — [% complete this period] — [% complete cumulative] — [notes]

Milestones this period:
  [M-ID] — [ACHIEVED on date / FORECAST date / DELAYED — new forecast]

Critical path status:
  Current critical path: [list critical activities]
  Float on near-critical activities: [days]
  Critical path change since last period: [yes/no — describe change]

Delay Analysis

When a delay is reported:

Step 1 — Classify the delay

TypeDescriptionEntitlement
Excusable compensableClient-caused (instruction change, late info, access denial)Time + money
Excusable non-compensableForce majeure, exceptional weather, third-partyTime only
Non-excusableContractor-caused (resource shortage, poor planning)No entitlement

Step 2 — Quantify

  • Identify the delayed activity
  • Check if it is on the critical path
  • If on critical path: delay to completion = delay to this activity (less any float)
  • If off critical path: no completion impact unless float is consumed
  • Calculate completion date impact

Step 3 — Document

DELAY RECORD
  ID: DEL-[NNN]
  Activity affected: [WBS reference]
  Delay type: [EXCUSABLE COMPENSABLE / EXCUSABLE NON-COMPENSABLE / NON-EXCUSABLE]
  Cause: [description]
  Duration: [calendar days]
  Critical path impact: [YES — N days to completion / NO — N days float consumed]
  Notified to client: [yes/no — date]
  Contractor notice received: [yes/no — date]
  EOT claim anticipated: [yes/no]

Step 4 — Recovery options

If delay impacts completion:

  1. Acceleration of successor activities (cost implication — route to cost)
  2. Re-sequencing (logic change — update schedule and re-check critical path)
  3. Additional resources (contractor cost — check contract for acceleration provisions)
  4. Revised completion date (notify client — route to report)

Earned Value Snapshot

At each reporting period (if sufficient data):

MetricFormulaValueStatus
Planned Value (PV)Budget for work scheduled
Earned Value (EV)Budget for work completed
Actual Cost (AC)Cost actually incurred
Schedule Variance (SV)EV − PV+ ahead / − behind
Cost Variance (CV)EV − AC+ under / − over
SPI (Schedule Performance Index)EV / PV<1 behind, >1 ahead
CPI (Cost Performance Index)EV / AC<1 over, >1 under
EAC (Estimate at Completion)BAC / CPI

Report to report if SPI < 0.85 or CPI < 0.90 — threshold for client notification.

示例提示词

工期有延误风险,帮我更新一下关键路径和挣值分析。

所属插件

建筑学与土木工程面向建筑与土木研究和设计:场地分析与方案设计、Revit/AutoCAD/Rhino-Grasshopper 与 OpenBIM-IFC、机电与结构协调、消防与无障碍、围护结构与日照能耗、造价与工程量,以及土木工程项目的进度、质量、安全、风险与 RFI 管理。

安装该插件会一并获得同领域的 44 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

土木项目进度管理能做什么?

Manages civil-engineering project schedules: WBS, critical path, earned value, and delay analysis in planning and execution modes. Use for milestone updates, delay events, or schedule review。

如何安装土木项目进度管理?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「土木项目进度管理」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

土木项目进度管理需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

土木项目进度管理经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。