Plans the path from idea to sellable product through EVT/DVT/PVT and mass production, with gates, durations, and long-lead purchases. Use to produce a dated roadmap.

发布者 Codar安全审核通过v0.1.0更新于 2026-11-18

SKILL.md

Prototype roadmap

Turn the design into a dated plan that a team can follow. Each stage has a deliverable and a gate. The plan shows the critical path and the date by which each long-lead part must be ordered. Write it to hw/roadmap.md.

Talk to the user in the user's language. Files are in English unless the user's project uses another language.

Prerequisites

Run commands from inside this skill's own directory (the folder containing this SKILL.md), since script and reference paths below (such as scripts/foo.py) are written relative to it, not to the project root.

Inputs

FileWhat you take from it
hw/brief.mdlaunch target, quantities, markets, budget
hw/state.jsonstage reached so far, gates already passed
hw/bom.csvlead_time_wk, stock_snapshot, lifecycle; custom parts (cell, molded parts, flex)
hw/power/whether the power budget is measured or only estimated
hw/compliance.mdcertification durations and blocking items ("Schedule hooks")
hw/cost/tooling and NRE lead times, MOQs
hw/doability/review.mdopen risks that need an experiment before a commitment

Outputs

  • hw/roadmap/stages.json: stages, dependencies, duration ranges, gates, milestones and long-lead items. The format is in templates/stages.example.json.
  • hw/roadmap/schedule.md and hw/roadmap/timeline.svg: generated by scripts/roadmap.py.
  • hw/roadmap.md: the plan, built from templates/roadmap.md, including the bring-up log.
  • hw/state.json: the current stage and the next gate.

Procedure

  1. Place the project. Decide which stage it is in: idea, Stage 0, Stage 1, EVT-n, DVT, PVT or MP. Use what has actually been built and measured. Do not use how finished the CAD looks: a collision-free 3D model means the industrial design is frozen, not the engineering.

  2. Write the stages JSON. Start from templates/stages.example.json, and remove the stages the product does not need. For example, a product with a catalogue cell has no custom-cell stage.

    • For each stage, give a [best, worst] duration in weeks, its dependencies (depends_on, optional lag_weeks, negative for overlap) and an exit gate. Take the gates from references/stages.md.
    • Use real lead times from hw/bom.csv, supplier quotes and hw/compliance.md where you have them. Tag each duration as verified or estimate.
    • Add a long_lead entry for every part whose lead time is 12 weeks or more, or whose stock is low, with the stage that first needs it.
    • Give each long_lead entry qty_needed and, when you have it, today's distributor stock: "stock": {"on_hand": 9278, "source": "LCSC", "date": "YYYY-MM-DD"}. When the order-by date from the factory lead time has passed but the stock covers qty_needed, the item is buy now from stock, not late. With too little stock or no stock data, it stays LATE and shows the shortfall.
    • Dependencies go in depends_on. The script rejects unknown stage keys, so a typo such as after fails loudly instead of silently starting the stage at week 0.
  3. Generate:

    python3 scripts/roadmap.py --stages hw/roadmap/stages.json --md hw/roadmap/schedule.md --svg hw/roadmap/timeline.svg
    

    Read the critical path, the "LATE" rows and the "in stock: buy now" rows. Look at the SVG before you embed it: stage names wrap between words, and milestone labels take separate lanes so they never cover each other. Test the script with python3 scripts/test_roadmap.py.

  4. Check the order of commitments. No custom cell, mold or board revision may start before the measurement that sizes it. If the plan has one, move it, or write down why the risk is accepted (hw/decisions.md).

    • The usual critical path: power measurement → cell decision → custom cell → UN 38.3 → certification → sale.
    • The final mold also waits for the cell envelope.
  5. Write hw/roadmap.md. The answer comes first:

    • where the project is now;
    • the first legal sale, best and worst case, and what drives it;
    • what to order now;
    • the next gate.

    Then give the timeline, the per-stage plans, an empty bring-up log and the schedule risks.

  6. During EVT and later, use references/bringup-checklist.md for each new board and log the results. Use references/test-fixtures.md to plan test access before routing, and fixtures before PVT.

  7. Hand off.

    • cost-and-sourcing takes the NRE timing and the long-lead purchases.
    • doability-review takes the stage the project is in and the uncommitted measurements.
    • product-presentation takes timeline.svg and the answer-first block.

Gate

The roadmap stage passes when:

  • every stage has a deliverable, a duration range with an evidence tag and an exit gate;
  • the critical path is identified, and no custom part starts before the measurement that sizes it (or the accepted risk is logged);
  • every long-lead part has an order-by date, and late items are reported to the user;
  • the first-legal-sale date is a range (best to worst), not a single optimistic date.

Taste and pitfalls

  • Measure first. The first engineering deliverable is often a measurement bench, not a PCB. Current measured on a dev kit with the real duty cycle sizes the battery, the memory and the enclosure.
  • The 3D model freezes the industrial design, not the engineering. Expect 3–4 board revisions and 1–2 mold iterations before mass production. Do not call a design "final" before it has been powered, measured, dropped and certified.
  • Quote ranges, never single dates. Teams that promise the best case to customers end up refunding pre-orders.
  • Order long-lead parts at once. Order EVT and DVT quantities as soon as a part is chosen. Lead times of 16–26 weeks are normal for springs, drivers and connectors, and stock can vanish.
  • Certification is on the path, not after it. In markets like Brazil, nothing with a radio can be sold before homologation, and that includes a small launch batch.
  • Design test access before routing: test pads, an RF test strategy and a test mode in firmware.
  • Bring-up closes with numbers. Every checklist line records a measured value and the instrument. "Seems fine" does not close a line.
  • Keep the roadmap honest. When a gate fails, move the dates and tell the user. Do not shrink later stages to keep the launch date.

References

  • references/stages.md: what each stage builds, the questions it answers and its gate, plus the critical path, long-lead parts and the iterations to expect.
  • references/bringup-checklist.md: step-by-step board bring-up, from before power to the system soak.
  • references/test-fixtures.md: design for test and the production fixtures, with NRE ranges.
  • templates/stages.example.json: an example plan for a fictional BLE fitness band.
  • templates/roadmap.md: the output template.

示例提示词

帮我规划一下从样机到量产的时间表和各阶段测试节点。

所属插件

电子电气与信息工程面向电气与电子工程研究:电力系统仿真(PSS/E、PSLF、PowerWorld、pandapower、PyPSA、OpenDSS、ANDES)与越限/稳定/短路处置,FPGA 时序收敛与跨时钟域检查,电路与 PCB 设计评审,硬件产品开发流程。

安装该插件会一并获得同领域的 63 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

硬件样机开发路线规划能做什么?

Plans the path from idea to sellable product through EVT/DVT/PVT and mass production, with gates, durations, and long-lead purchases. Use to produce a dated roadmap。

如何安装硬件样机开发路线规划?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「硬件样机开发路线规划」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

硬件样机开发路线规划需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

硬件样机开发路线规划经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。