Playbook for N-1/N-2 contingency violations: ranks contingencies and proposes preventive and corrective actions. Use after a study shows voltage or thermal problems.
SKILL.md
Contingency mitigation
Start with a solved base case and a ranked list of critical contingencies.
Preferred action order
- Verify the contingency definitions, monitored elements, and limits.
- Group critical contingencies by common corridor, interface, or weak area.
- Apply preventive actions first: redispatch, shunts, tap changes, or topology changes that help multiple contingencies.
- Evaluate corrective actions next: post-contingency switching, redispatch, or RAS schemes with explicit triggers.
- Re-run the full monitored set after any candidate fix. If violations remain, return to step 3 with updated rankings.
- Use load shedding only as a last-resort action and state that clearly.
- For recurring problems, recommend reinforcement or a revised operating guide.
Worked example
The N-1 loss of Line X-Y overloads Line A-B to 108% of rating and pulls Bus C down to 0.91 pu. Grouping the violations shows both sit on the same east-west corridor, so one preventive action can cover the family: 60 MW of redispatch from G1 to G4 clears the thermal violation, and switching in the 50 Mvar capacitor bank at Bus C restores the voltage to 0.97 pu. Re-running every monitored contingency confirms no new violations.
Working rules
- Do not trust contingency results from a bad base case.
- Prefer actions that improve a family of contingencies rather than a single outage.
Deliver
- The critical contingencies and the shared weak pattern.
- The best preventive action.
- Any corrective action that is still required after prevention.
示例提示词
N-1分析发现了越限,帮我分析原因并给出处置方案。
所属插件
安装该插件会一并获得同领域的 63 个 Skill / MCP。
同插件的其他科研 Skill
- ANDES电力系统动态仿真Runs ANDES power-system dynamic studies via PowerMCP: power flow, eigenvalue analysis, and time-domain simulation. Use for damping, stability, or oscillation-mode questions.
- 电池选型与电源预算Builds an evidence-tagged power budget and sizes a manufacturable battery with pouch outline, seals, and derating. Use when sizing runtime, mAh, charging, or supply rails.
- FPGA比特流生成与烧录Generates a Xilinx FPGA bitstream and programs it over JTAG, or burns an MCS image into flash for power-on boot. Use when flashing a board or diagnosing boot failures.
- 硬件项目发布包组装Assembles a hardware release package (fab files, BOM/CPL, carts, assembly guide, hashed manifest) and runs a ready-to-build gate. Use before ordering prototypes.
- 时钟域交叉风险审查Audits clock-domain-crossing risk on an FPGA design and applies the smallest safe synchronizer or constraint fix. Use to resolve CDC violations before sign-off.
- 硬件产品认证合规规划Plans certifications a hardware product needs per target market (FCC, CE/RED, UKCA, battery/radio rules), with cost and lead-time estimates. Use before PCB or enclosure tooling.
- Vivado XDC时序约束编写Authors a Vivado XDC timing constraint set from scratch: clocks, I/O delays, and timing exceptions. Use first, before timing closure, on a design with no or incomplete constraints.
- 潮流计算不收敛诊断Playbook for power-flow convergence failures in PSS/E, PSLF, PowerWorld, pandapower, PyPSA, surge, or OpenDSS. Use when a case diverges or fails to solve.
- 硬件成本核算与采购Prices a hardware product at multiple volumes with one-time vs per-unit cost, landed cost per country, and sourcing leads. Use to estimate unit cost before a pitch.
- RTL仿真覆盖率收敛Measures RTL simulation code coverage and iteratively closes it toward a target by adding testbench stimulus. Use for a sign-off-grade coverage report.
- 配电网DER接纳能力治理Playbook for distribution DER hosting-capacity limits: voltage rise, reverse flow, and thermal limits from PV and storage. Use to estimate how much DER a feeder can host.
- 电子电路设计与审查Designs, audits, or corrects an electronic circuit from a brief, schematic, or netlist, checking power domains, reset sequencing, and ratings. Use for circuit review.
- 硬件可制造性红队审查Red-team audit that fix-loops a hardware project to ready-to-build, re-deriving parts, rails, battery physics, and cost. Use for a reality check before committing to a design.
- 电力系统动态稳定处置Playbook for dynamic stability problems: poor damping, angle instability, or sustained oscillations from eigenvalue or time-domain studies. Use after an unstable study result.
- Egret电力市场调度优化Runs Egret market/operations optimization (DC-OPF, AC-OPF, unit commitment) via PowerMCP. Use for cheapest dispatch, unit commitment, or congestion checks.
- 电子元器件选型核查Researches electronic components against primary sources: part numbers, datasheet limits, lifecycle, stock, and price breaks, one dossier per part. Use to verify or source a BOM.
- EMC电磁兼容预测试Plans grounding, shielding, and filtering for EMC/EMI, and runs an emissions pre-scan with a root-cause fix sequence. Use before a lab test or after a failed EMI scan.
- 产品外壳参数化建模Designs a hardware enclosure as parametric CAD with STEP/STL/GLB output, a DFM check, and Blender assembly validation. Use when designing a case or checking fit.
- 电网频率响应问题处置Playbook for frequency problems: low inertia, high RoCoF, weak primary response, or UFLS risk after loss of the largest unit. Use when a study flags frequency issues.
- FPGA RTL到比特流全流程Drives a Xilinx FPGA design end to end through RTL, simulation, synthesis, implementation, and bitstream, gated at every stage. Use to run the complete build flow in one pass.
- 硬件产品全流程总协调Leads a physical electronic product from idea to a doable design, coordinating specs, parts, battery, PCB, enclosure, render, and cost sub-skills. Use starting a hardware product.
- 硬件原理图与BOM审查Reviews hardware projects: checks schematics against datasheets, pin connections, and firmware-to-hardware alignment across KiCad/Altium files. Use for a design alignment check.
- FPGA ILA在线逻辑调试Inserts an Integrated Logic Analyzer, programs the board, arms a trigger, and reads captured waveforms on real FPGA hardware. Use when sim passes but the board fails.
- 新能源并网影响评估Playbook for screening the grid impact of a new generator, storage, or large-load interconnection. Use to check whether a given MW can connect and what upgrades it needs.
常见问题
N-1/N-2应急违规处置能做什么?
Playbook for N-1/N-2 contingency violations: ranks contingencies and proposes preventive and corrective actions. Use after a study shows voltage or thermal problems。
如何安装N-1/N-2应急违规处置?
在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「N-1/N-2应急违规处置」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。
N-1/N-2应急违规处置需要哪些权限?
该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。
N-1/N-2应急违规处置经过官方审核吗?
是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。