Playbook for screening the grid impact of a new generator, storage, or large-load interconnection. Use to check whether a given MW can connect and what upgrades it needs.

发布者 Codar安全审核通过v0.1.0更新于 2026-11-18

SKILL.md

Interconnection impact mitigation

Start with a defined injection: MW and MVAr capability, the point of interconnection (POI), and the dispatch scenarios to study.

Preferred action order

  1. Pin down the study scenario set: peak and off-peak cases, high-renewable dispatch, and the prior-queued projects that must be modeled as in-service.
  2. Run steady-state screens with the addition: base case and N-1 power flow, thermal loading and voltage screens around the POI. Route violations to thermal-overload-mitigation and voltage-violation-mitigation for the corrective toolkit.
  3. Check weak-grid risk for inverter-based resources: short-circuit ratio at the POI. Low SCR (roughly below 3, critical below 2) flags control-interaction and stability risk — consider grid-forming controls, synchronous condensers, or POI relocation.
  4. Verify reactive capability and voltage control: power-factor range and voltage ride-through at the POI against the applicable interconnection requirements.
  5. Identify the binding constraint and assemble the mitigation set: network upgrades, an output-limitation or curtailment agreement, reactive devices, or phased interconnection — sized to the smallest set that clears the binding screen.

Working rules

  • Screen with linear tools (PTDF on the injection) before full N-1 reruns; confirm the short list in AC.
  • The fault contribution of the new plant changes breaker duty nearby; screen it and route over-duty to short-circuit-mitigation.
  • Restudy after any material change in plant size, POI, or queue assumptions — interconnection results do not transfer between scenarios.
  • Separate "needed to connect safely" from "needed to deliver full output" — reliability upgrades and deliverability upgrades have different urgency and cost allocation.

Deliver

  • The injection studied (MW, POI, scenarios) and the screens it passed.
  • The binding constraint with numbers (element, loading or voltage, contingency).
  • The recommended mitigation set and what must be restudied if assumptions move.

示例提示词

帮我评估一下这个新电站在该并网点能接入多少兆瓦并给出方案。

所属插件

电子电气与信息工程面向电气与电子工程研究:电力系统仿真(PSS/E、PSLF、PowerWorld、pandapower、PyPSA、OpenDSS、ANDES)与越限/稳定/短路处置,FPGA 时序收敛与跨时钟域检查,电路与 PCB 设计评审,硬件产品开发流程。

安装该插件会一并获得同领域的 63 个 Skill / MCP。

同插件的其他科研 Skill

常见问题

新能源并网影响评估能做什么?

Playbook for screening the grid impact of a new generator, storage, or large-load interconnection. Use to check whether a given MW can connect and what upgrades it needs。

如何安装新能源并网影响评估?

在科搭 Codar 左侧点击「插件」,在「组件」页签搜索「新能源并网影响评估」并安装;在 Claude Code 或 Codex 中可以发送本页的安装提示词,或下载 Skill 包后解压到 ~/.claude/skills 或 ~/.codex/skills。

新能源并网影响评估需要哪些权限?

该科研 Skill没有声明额外权限;执行具体操作时仍由 Agent 按自身规则请求确认。

新能源并网影响评估经过官方审核吗?

是。SpeedSkills 收录的每个版本都会记录内容摘要与权限声明,当前版本已通过安全审核。